DDC Rajouri reviews progress on JPDCL projects

J&K/Rajouri (The Stellar News), Anil Bhardwaj: To review the progress on JPDCL projects being executed by the Project Wing in the district, District Development Commissioner Rajouri, Rajesh K Shavan on Monday convened a meeting with the concerned officers and contractors here in his office chamber.

Advertisements

The meeting was attended by the Chief Planning Officer, Mohammad Khurshid; Superintending Engineer Project Circle JPDCL, Neeraj Sharma; Project Manager Reliance New Delhi and Project Manager Power Tech Engineering Noida.

DDC took a detailed review of the physical and financial status of the projects being undertaken under various schemes like IPDS, PMDP Urban, DDUGJY and PMDP Rural in the district.

While reviewing the progress on PMDP rural, it was informed that as many as 04 receiving stations and 74 transformers were to be erected in the rural areas of the district out of which 33 transformers stand erected and the work on one receiving station out of four is complete.DDC asked the concerned project Manager to complete the work on erection of 25 more transformers by 25th March this year.

About DDUY, it was apprised that out of 19 new creations including transformers and receiving stations, the work on 15 is complete and the rest are under different phases of execution.DDC fixed the deadline of 15 April this year to complete the work of all the pending creations.

Regarding the PMDP urban, the meeting was informed that out of 25 transformers to be erected in sunderbani town, the work on 15 is complete in all respects.In Nowshera town against the target of erecting 23 transformers, the work on 13 is complete.Similarly in Rajouri and Thanamandi town, against the target of erecting the 36 transformers in Rajouri and 14 transformers in Thanamandi, the work 18 transformers in both the towns is complete.

Similarly the DDC also reviewed the progress on physical and financial on all the works being executed by the project Wing in the district.

DDC asked the Project Managers of the Companies executing the works under different centrally sponsored schemes of the JPDC to work in double shifts to complete all the pending works within the set deadlines to provide necessary benefits to the common masses.